How to make Curriculum Vitae?
For visitors who have problem about Curriculum Vitae. I give one of CV sample. You are able to see the below:
| Proposed Position
Personal Data
|
Managing Quantity Surveyor | |
| Name
Date of Birth Nationality Civil status |
Moch.Gatot Wiharto
29.01.1964 Indonesia Married |
|
| Education | University of Indonesia Islamic
Bachelor of Civil Engineering 1993 |
|
| Languages | Speaking : fair, Reading : fair, and Writing : good | |
| Geographical Experience | Indonesia, Libya | |
| Key qualifications
|
I have more than 16 years of general experience and at least 1 years experience within international contractor. | |
| Career Highlights | Experience Summary | |
| Date from – Date to
Company Location Position |
Project Name
Project Description Responsibilities/Tasks
|
|
| Project Name
April 2008 – April 2009 CILJV(CKG IKPT LIBYA JOINT VENTURE) Libya
Quantity Surveyor |
Ain zara Apartment Complex Project, LIBYA
Project Description: 156 Buildings in Ain Zara project area, There are comprise 106 buildings of office and 5 tower buildings. This is area built School buildings start from kindergarten, primary, high school. Hospital is available and making Infrastructure with underpass The building on raft foundation with reinforced concrete. There are several building variant storey that of 5, 6, and 7. Value US$ 10 billion Responsibilities/Tasks: Leaning contract system between CILJV among sub-contractors. Estimating and controlling all materials that used contractor although sub-contractors. Checking progress project that proposed sub-contractor with quantity surveyor calculation result interim payment application then submitting it to Project Manager. To make monthly progress project. |
|
| Project Name
Feb 2006 – March 2007 PT.Arkonin CM Jakarta Construction Manager |
Carrefour retail
Project Description: Building area 8,000m2. It is completed with escalators, air conditioner central, barcode system alarm, parking area, and sanitary system. Value US$ 4 million Responsibilities/Tasks: Prepare, issue and manage the Master Schedule and Milestone of Project, including the identification of the constrains of the project from the Design / Engineering phase till the end of project. Check and recommend the contract award for Owner’s approval evaluated and submitted by QS and CM Consultants. Check and recommend the contract award for Owner’s approval evaluated and submitted by QS and CM Consultants. Check and approve the contract documents for signing by the Owner. Coordinate all aspects of the Project Management including program, engineering and finance of the project. Lead and direct the coordination meeting with Consultants (A/E, CM and QS), and with contractors (if necessary).Prepare and issue the brief periodic project progress report in the aspect of program, engineering and finance. Recommend the Project Cash Flow, submitted by QS for Owner’s approval. Recommend to the Owner’s, the contractors progress payment approval QS. Recommend to the Owner’s, the contractors claim due the change order, force majeure. Approve all certification guarantees, operation manual and other document necessary for the operation, submitted by CM. Approve all document and certificate related to handing over process of the work, submitted by CM and QS. Approve Project Final Report, submitted by CM and QS
|
|